Many federal janitorial and grounds solicitations name a date when the agency will walk interested companies through the buildings or grounds. It is usually the only time before the due date that you can see the floors, restrooms and conditions you are about to price. This page explains what the rules say about site visits, what to look at, and what happens to the questions you raise. For the overall bidding steps, see how to bid on federal janitorial contracts.

It explains how the process works. It is not legal advice; your state's free APEX Accelerator can help with a specific solicitation.

1. What the solicitation says about it

For service contracts performed on government installations (other than construction), the contracting officer puts the Site Visit provision in the solicitation (FAR 37.110(a)). Its text is short (FAR 52.237-1):

So the provision itself urges a visit rather than requiring one. The cost of what you would have seen is yours either way: if you skip the visit and the floors turn out to need stripping every month, that is not grounds for a price increase. Some solicitations go further and make attendance a condition of bidding; read the instructions to offerors to see which applies.

2. Site visits and pre-proposal conferences

The FAR lists pre-proposal conferences and site visits among the ways agencies exchange information with companies before offers are due (FAR 15.201(c)). A conference is a briefing, often in a meeting room or online; a site visit is the walk-through. Some notices combine them. Find in the notice or its attachments:

3. What to check on a cleaning or grounds walk-through

The work statement gives square footage and frequencies. The visit tells you what those numbers mean in labor hours. Useful things to note:

Take notes and photos only where the agency allows it; secure facilities often don't.

4. Questions, answers and amendments

What you are told on the walk-through is not the same as what is in the solicitation. To rely on something, ask it in writing by the questions deadline.

5. If you can't attend

Read the instructions first: if attendance is required, missing it can rule you out. If it isn't, you can still read the attendee list and Q&A when the agency posts them, ask your own questions in writing by the deadline, and look at whatever public areas you can reach. You carry the risk of anything a visit would have shown (FAR 52.237-1), so price that uncertainty or pass on the bid.

Where we fit

Site visit dates are often the first deadline in a solicitation, sometimes only a week or two after it posts. The free weekly list sends you the open janitorial and grounds solicitations plus upcoming rebids, your state first, so you see them in time. The bid desk ($149 a month, 14-day trial) adds a go/no-go note on each one, and we can draft the response when you decide to bid.